newsConstruction Progress - CCSD 93's Early Childhood Center


Construction Progress - CCSD 93's Early Childhood Center

05/09/2013

Metal stud exterior framing nearing completion; Roof joists installed on building addition; Scaffolding erected and loaded prior to face brick installation; Roof insulation and ice and water shield installation; Roof shingle installation; Plenty of activity on the white single-ply roof membrane; Mechanical, electrical and sprinkler rough-ins; Hollow metal frames installed in metal stud walls.