Fairview SD 72 Construction Update

Time for a construction update from Fairview District 72! Our masons from Mastership Construction have been hard at work getting the walls up at Fairview South. The CMU walls on the Laramie Avenue side of the building and the west side of the Pre-K/Kindergarten wing are up! If you look closely the CMU wall is being shored, or temporarily supported, with steel on large concrete piers.
The team also completed the storm trap units, the next step is backfilling.